Heritage House Condominium Association
Updates on Reconstruction
From the Heritage House Condominium Association Board of Directors
TO: Heritage House
Condominiums
Board of Directors
FR: Jim Driscoll
Nyman Construction
RE: Construction
Progress Update
DATE:
The rough-in sprinkler work continues and will be
finished shortly.
During the installation of the sprinklers in units 117-127, 217-227 and 317-327, your insurance adjusters
inspected the insulation above the ceilings only to discover smoke
damage. They immediately notified the adjuster for State Auto. Upon re-inspection by both parties it was
determined that the ceilings in the aforementioned units would need to be taken
down, the insulation removed and new insulation installed. They also
agreed that the carpet would be removed and new carpet installed. The
units would also be completely repainted. In anticipation of the
work, Nyman has inventoried all the ceiling electrical and HVAC fixtures in
each unit before removing and storing for later re-installation.
The HVAC duct work has been roughed-in on the third
floor and work has begun on the second floor.
The elevator prep work continues. New elevator
foundations and floors should be poured this week.
Framing of units 301-316 should begin shortly.